Update 1
It’s been some time since our launch, and much has been happening on the ground!
Here are some updates:
All permits and construction certificates are now in hand from MidCoast Council
Authorised tree removal has taken place to clear the site for construction, with a couple of coral trees to go
Removal of the ‘old stage’ building has taken place
New connections for power, water have been completed, new sewer estimated completion end of July
Ground improvements for building foundation have started, due for completion late July
Carpark to be complete end of August
Temporary Green Cathedral path access in place
What’s next?
Tender process for building work
Further fundraising